Co-Gen Steam Turbine Plinth Strengthening

  • Company: CHH Kinleith
  • Location: Kinleith, New Zealand
  • Date: September 2012
+ Overview

CMS were engaged in a project at Kinleith Mill to move specific sections of steam, lube oil, cooling water and condensate lines, followed by fabricating and installing all new lines in their new routes.

There was 100% visual inspection and radiography testing of every weld done.

= Outcome

Completed on budget, 1 day ahead of schedule, with no LTI’s

CMS Project Supervisor
Tony Jump

Project Manager
Graeme Sutherland